There are two feeding methods for concrete mixing plants, belt conveyor feeding or hopper feeding. The former is mostly used in large stations, the latter is mostly used in small and medium-sized stations, and the material is loaded by the hopper that comes with the mixer. The structure of JS compulsory concrete mixer is composed of feeding, mixing, water supply, electrical, unloading, construction site, cover, outriggers and other parts. When working, the electromagnetic brake motor drives the reel to rotate through the reducer, and the wire rope climbs up along the rail of the loading rack through the pulley pulling the hopper. When it climbs to a certain height, a pair of rollers on the bucket door at the bottom of the hopper enters the horizontal fork of the loading rack, the bucket door It is automatically opened, and the material is poured into the mixing tank through the feed port on the cover.
Concrete mixing station feeding system
Problems and solutions in the loading of concrete mixing plant
1. The feeding operation is not stable; the reason: the feeding track is warped and uneven, and the hopper roller is in poor contact; the solution: check and adjust the two tracks to make the tracks straight and parallel.
2. The traction mechanism is broken by passing the top dead point when the material is being loaded up; reasons: (1) the automatic limit device fails, (2) the automatic limit baffle is deformed and does not work; solution: (1) repair or replace The limit device (2) adjusts the limit baffle.
3. The hopper is stuck when loading; reasons: (1) the guide rail is not installed flat, (2) there is foreign matter in the hopper discharge door; solution: (1) re-leveling, (2) removing foreign matter.
4. The lower mouth of the hopper does not load when feeding; reasons: (1) the wire rope is elongated, (2) the wire rope clamp is loose; solutions: (1) adjust the rope buckle to tighten it, (2) tighten the wire rope clamp.